City of Laramie and Knife River To Begin Street Rehab 

 

Laramie, Wyoming – The City of Laramie partnered with Knife River to begin a massive rehabilitation project for 9 lane-miles of mill and overlay with associated curb and gutter, ADA ramps, and spot base repair this summer. The following is the initial project schedule. Dates are approximate and may change due to weather, field conditions, and construction progress.

Concrete Work (curb/gutter, sidewalk/ADA, and base repairs as applicable)

  • 4th St – Flint St to Clark St — starts Mar 6, 2026
  • Skyline Dr — starts Mar 13, 2026
  • 4th St – Clark St to Ivinson Ave — starts Mar 20, 2026
  • Adams St — starts Mar 31, 2026
  • Ivinson Ave — starts Apr 2, 2026
  • McCue St — starts Apr 9, 2026
  • Spring Creek Dr — starts Apr 23, 2026
  • 22nd St — starts May 13, 2026
  • Sheridan St — starts May 27, 2026
  • Reynolds St — starts Jun 10, 2026

Asphalt Work (utility adjustments as needed, milling, patching/subgrade repair, and paving)

  • S Colorado Ave — starts May 1, 2026
  • 4th Street — starts May 6, 2026
  • Ivinson Ave — starts May 18, 2026
  • Skyline Dr — starts Jun 11, 2026
  • McCue St — starts Jul 1, 2026
  • Spring Creek Dr — starts Jul 14, 2026
  • 22nd St — starts Jul 22, 2026
  • Sheridan St — starts Aug 6, 2026
  • Reynolds St — starts Aug 26, 2026
  • Adams St — starts Sep 10, 2026
  • General Brees — starts Oct 2, 2026

The entire rehabilitation project will be wrapped up by the end of October 2026. Each roadway being rehabbed will be closed for not more than four weeks while crews work. Traffic will be redirected as needed for the safety of crews, pedestrians, and drivers alike. 

The public can find out which streets are on the shortlist for closure or are currently closed by visiting the City of Laramie Road Closures link. The public will also be able to follow along on project progress by signing up for the City’s Newsflash tool at www.cityoflaramie.org/m/newsflash. There will be monthly and major project updates [WW1] on road closures and rehab progress posted there. 

For more information, please contact Ridge Leinen in the City of Laramie Engineering Division at engineering@cityoflaramie.org or 307-721-5250.

-END-


  1. Web Logo white

    406 Ivinson Avenue

    Laramie, WY 82070


    Phone:  307-721-5200

    Monday - Thursday: 8 a.m. - 4 p.m.

    Friday: 8 a.m. - 2 p.m.

Share

Site Tools

Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow